SPACE BOARD
| Download PDFs | ||
|---|---|---|
- Designed for use over existing loft boards
- Saves energy and reduces heating costs
- Creates a warmer home in winter, cooler in summer
- Quick and easy to cut and fit
- Exceptional compressive strength.
| Thickness (mm) | Width x Length(mm) | Area per board (m2) | R-Value (m2K/W) | Thermal Conductivity (W/mK) |
|---|---|---|---|---|
| 52.5 mm | 1200 x 500 | 0.6 | 1.8 | 0.029 |
Find out where you can buy Space Board here.
Space Board can be installed either in an empty loft or over existing chipboard.
- Provides a robust insulated storage platform
- Reduces heat loss through the roof of your home
- Saves energy and reduces heating costs
- Ideal for use in conjunction with Space Blanket
- Warmer home in winter, cooler in summer
- Quick and easy to cut and install

Installing Space Board in an empty loft
STEP 1- Ensure bottom layer insulation is installed between ceiling joists
STEP 2- Run a 10mm-15mm bead of solvent-free adhesive along the joists and then lay Space Board at right angles across the joists in the designated storage area. Apply pressure to each board as it is laid to ensure good adhesion between the board and joists. Each 1200mm long Space Board should be typically supported by 3 joists
STEP 3- Lay second layer of Space Board over first layer, stagger the boards and glue all joints to ensure a flat, secure deck
STEP 4- Lay chipboard deck and glue all tongue and groove joints in the deck
STEP 5-Install top up insulation around the designated Space Board storage area(i.e. over ceiling joists)
Note: Ensure ceiling joists can bear extra loads due to storage.
Electrical cables should be located above the new deck
Installing Space Board over existing chipboard
STEP 1- Remove all stored goods from existing loft boards and clean thoroughly
STEP 2- Run a 10mm-15mm bead of solvent-free adhesive along the joists and then lay Space Board over existing boards. Applying pressure to each board to ensure good adhesion between the Space Board and loft board.
STEP 3- Lay second layer of Space Board over first layer, stagger the boards and glue all joints to ensure a flat, secure deck
STEP 4- Lay chipboard deck and glue all tongue and groove joints in the deck
STEP 5- Install top up insulation around the designated Space Board storage area (i.e. over ceiling joists)
Note: Ensure ceiling joists can bear extra loads due to storage.
Electrical cables should be located above the new deck